Data Centers
From this page you should learn
What are data centers and their role in the Internet
How they connect to the Internet
How they are structured and connect internally
The term "data center" is applied to at least 3 types of facilities.
In the original meaning, data centers are facilities that store and
distribute the data on the Internet. With an
billion plus web pages data
centers contain a lot of data. With almost two billion users
accessing all these websites, including a growing amount of
high bandwidth video, it’s easy to understand but hard to
comprehend how much data is being uploaded and downloaded
every second on the Internet.
What are called AI data centers include computational facilities for
artificial intelligence. These serve users of AI but also are used to
train AI using data on the Internet and local. They are similar in
architecture to an Internet data center but add large numbers of high
powered processors mostly based on graphics processing units (GPUs)
developed for processing video. Some now call these "AI factories."
Standards for data centers take a more generalized
view of what is a data center. A data center, as defined in TIA-942, Telecommunications
Infrastructure Standard for Data Centers, is a building or
portion of a building whose primary function is to house a
computer room and its support areas. That definition seems
quaint in the era of giant warehouse-sized data centers with
hundreds of thousands of servers, switches and storage and
up to a million interconnections.
The main functions of a data center are to centralize and
consolidate information technology (IT) resources, house
network operations, facilitate e-business and to provide
uninterrupted service to mission-critical data processing
operations. Yes, it is what we used to call the computer
room before it grew to fill giant buildings! Data centers
can be part of an enterprise network, a commercial venture
that offers to host services for others or a co-location
facility where users can place their own equipment and
connect to the service providers over the building’s
connections.
Data centers can be big like a Google, Facebook,
Amazon or Apple data center - called hyperscale data centers. Google has has
some very artistic photos taken of their data centers and
put them online so all can see them. You can learn more
about Google’s data centers here: http://www.google.com/about/datacenters/inside/
The really giant data centers today are those used
for AI computing, which should some now call "AI factories" instead of
data centers because their functions are more to support AI computing
than serving data for the Internet.
Or small like what we used to call the computer room - this
one at the new San Diego public library. It's just big
enough to store some basic library data and be the nerve
center for their passive optical LAN (POL.)

Data centers are filled with tall racks of electronics
surrounded by cable racks. And power cables. And cooling
equipment. Data has been typically stored on big, fast hard drives but is now mostly on solid state drives.
Servers are computers that take requests and move the data
using fast switches to access the right hard drives. Routers
connect the servers to the Internet. Speed is of the
essence. Servers are very fast computers optimized for
finding and moving data. Likewise, the storage, switches
and routers are chosen for speed. Interconnection use the
fastest methods possible. Faster speed means lower latency,
the time it takes to find and send the data along to the
requester.
While speed is a primary concern for data centers, so is
reliability. Data centers must be available 24/7 since all
those 2 billion Internet users are spread all around the
world. Reliability comes from designing devices with
redundancy, backups for storage, uninterruptible power and
fighting the #1 enemy of reliability, heat.
Heat is generated by all the electronics, and the faster
they run, the more power they consume and the more heat they
produce. Getting rid of heat requires lots of air
conditioning which can consume as much power as the data
center electronics itself. Uninterruptible power requires
generators, batteries or even fuel cells and those generate
heat from inefficiency also.
Data centers consume vast amounts of power. A few years ago,
the magnitude of this consumption became apparent in surveys
of giant data centers. Estimates are that data centers
consume more than 3% of all the power consumed in the US,
which hosts the majority of data centers, an amount more
than consumed in total by almost half the states! Power
consumption in a data center is more than 100 times as much
per square foot as the average commercial property.
Within the data center, the focus is on moving data,
reducing power and heat and ensuring reliability. That’s
done by choosing components and systems, designing
facilities and installing them properly.
For the fiber optic tech working in a data center, it is a very large
number of cables and fibers to support the electronics with redundant
high speed connections. High fiber count cables, dense multifiber
connectors and racks, etc. are normal in a data center.
Data Center Building Design
The internal layout of a data
center depends on the type (computer center, hyperscale, AI, colocation, etc.)
That’s a big subject! A schematic of a typical data center is shown.

Note the
entrance facilities, a good place to start. The data center stores and served
data to the Internet so one expects multiple connections to telecom services.
Often the connections are duplicated for reliability and security since the
fiber optic cables used for connections are vulnerable to dig-ups or other
failures.The entrance facility will be filled with
electronics for the services connected so power and AC are important like the
rest of the data center.
Power is always a concern. A hyperscale or AI data center
can use as much power as a small city. Data centers are usually sited near a
substation where power is available and cheap. Inside the data center power is
conditioned for electronics and multiple backups available – batteries for
instantaneous backup, generators or fuel cells for long term backup. AI data
centers are known for having enormous swings in power consumption which can
disrupt the conventional power grid, so some use dummy loads that are switched
in and out to even the load on the grid.
Cooling is a major problem; high
speed electronics consume lots of power and generate lots of heat. Cooling may
be air or liquid or both, with electrical power needed for AC and water for
cooling like a power generating station.
Security is a major issue, and not
just cybersecurity. Access to the building, starting at the parking lot and
continuing at the entrance into offices, then again into the data center
entrance room, power, computing facilities, etc. Security is usually by card
access with metal detector and X-ray screening like an airport.
Data Center Electronics Architecture
The data center serves the LAN and WAN. The data
center is comprised of switches connecting the users to
servers and more switches [S} connecting servers [C] to
storage [D]. This is probably a good point to say that
data centers follow typical high tech linguistics – it has
its own language and many TLAs (TLA = three letter acronym)
– sometimes different from vendor to vendor. We will try to
avoid this language issue by using plain English.

Data center architectures often include redundancy and
multiple connections between servers, storage and switches.
That’s what’s generally called a “mesh” network because when
you draw in all the connections it looks like a mesh. That
also means data centers can have very large numbers of
cables to make all these connections.
Co-Location Data Centers
Some data centers are co-location centers where customers
can place their equipment in a warehouse type location which
provides power, AC and service provider access (as well as
high levels of security. Customer equipment is generally in
a "cage" - literally, a wire cage structure - and may
connect to carriers at an entrance facility cage and other
co-location customers in what is generally called a "meet
me" cage that allows connections without going outside the
facility on service provider links.
Data Center
Architecture
Because of the number of servers typical in a data center, a
tiered architecture of switches are used. Access switches
connect groups of servers and interconnection switches
connect the access switches. Some architectures have added a
third level of switches but since that adds complexity, cost
and latency pus used more power and creates more heat, a
more streamlined architecture is being used by many data
centers.

Like most tech areas, different vendors or groups have
different names for some of these components. This switch
architecture is sometimes called “fat-tree” or
“Spine-leaf.” Interconnection switches (also called
aggregation switches) may also be called core switches and
access switches may also be called edge switches. Earlier
designs used another (higher) layer of switches (core
switches) that users realized were not necessary,
practically doubled the cost and added heat and latency.
Servers may have direct storage connections on Ethernet,
Fibre channel (yes, it’s spelled “fibre”) or FCOE – Fibre
Channel over Ethernet or servers may connect to SAN switches
which then connect to storage. Server connections to the
storage area network (SAN) switches may be direct or through
the access and or interconnection switches.
Of all these connections, generally only the server-access
switch connections may be on copper up to 10G.
Below
we have expanded the network architecture to include the
routers
connecting the data center to the LAN and WAN (outside
world).

Then we have expanded the network architecture to include
the storage are network (SAN) connecting storage to servers.
When you consider the number of units connected and the
multiple connections often used for redundancy to ensure
reliability, you can see the amount of cabling that a data
center can include. Mesh switching links allow servers to
more easily use virtualization where one switch can provide
services to more storage with lower cost and power usage.

The use of data centers for AI computing adds another section of hardware used for AI computing.

The AI computing functions use very high speed computing devices
originally used for high speed graphics computing which are used for AI
to input large amounts of data and calculate AI using predictive
algorithms. This adds a section for AI computing which uses many
processors and a layer of GPU switches to find data for training or
supporting the AI. The GPU switches have connections to both SAN
switches for searching local data and access switches for searching the
entire Internet.
Standards For Data Centers
Architecture And Hardware
Until recently, data center architecture was
specified by vendors who provided the hardware - switches
and servers. With the advent of the mega- and hyper-scale
data center, big users began to look for more efficient (and
economic) ways to design and build data centers. This led to
in-depth analyses of
the way data centers were being built and how standards
are being developed, specifically the move to singlemode
fiber to allow equipment upgrades without cabling
changes and "open-sourcing" the design of
electronics.
Open
Compute Project - OCP is a user group started by
Facebook because traditional vendors were not delivering
the solutions needed. Traditional server/switch vendors
were not delivering products with the performance/price
needs of users in mind. Standards for data center
cabling were not based on the realities of the business.
In this case, the "realities" of the business was that
technology was requiring upgrades to the data center
every 18-24 months, way too fast for traditional
switch/server manufacturer product upgrades and the
typical 5-year cycle of standards development. Plus
hyper-scale data centers had as many as 100,000 to 1
million connections, demanding the most cost-effective
solutions.
OCP, driven by Facebook, started by developing their own
switches and servers and building the products
themselves. Then they put the designs online - open
source - and told everybody to try to make them better
and/or cheaper. Before long,
all the owners of large-scale data centers became
members of OCP. Then they knew it was necessary to use
singlemode cabling to be able to upgrade electronics
without replacing cabling, so they worked with
transceiver vendors for specific data center products
that cost substantially less than transceivers for
typical telecom use.
That this model can work for OCP has shown that it is a
valid model for developing standards - in fact it may
prove to be a better method. When products reach
commodity status - like data center servers and switches
and their fiber optic transceivers - the input of real
customers - not just manufacturers - is absolutely
necessary to get the product designed right. And regular
standards and product development cycles are way too
long to be useful.
Following the success of OCP, LinkedIn started Open
19 to cover lower cost equipment for smaller data
centers.
Reliability
Reliability is a primary concern for data centers as
downtime can be very painful to everyone. What defines
reliability? UL's
web page on their Data
Center Certification Program states "The
UL Data Center Certification Program will address
the continued reliability of key components of
critical data center infrastructure by integrating
the multiple disciplines of electrical,
mechanical, security, life safety, building
automation, and telecom to create a comprehensive
service." This is similar to the Uptime
Institute's Tier Certifications or the European
Standard EN 50600 by CIS.
Cabling
Some data Center cabling is
covered by TIA-568 and ISO-11801 through several standards,
ISO 24764, CENELEC EN 50173-5 and TIA-942. These standards
cover similar topics and offer lots of options for cabling
in data centers. They also include more TLAs (three letter
acronyms) than most standards. Many find the idea of
standards like those covering structured cabling irrelevant
for data center technology. It is difficult to be
relevant in a technology that upgrades entire facilities -
often including architectures - every 18-24 months when
standards have 5-10 year update cycles. Perhaps they make
sense for a small corporate data center/computer equipment
room but probably not larger data centers.
TIA started ~2006/7 to create a standard for data centers.
Perhaps as a consequence of the length of development and
review cycles for TIA standards, perhaps because it was
created by vendors trying to apply TIA-568 structured
cabling philosophy to data centers, it appears to be out of
touch with current data center design, especially hyperscale and AI data centers. Unlike an enterprise
LAN where one can conceivably create a cabling system that
is applicable to many types of users (LANs, video,
telephones, building security and management, etc.) data
centers are highly specialized and designed for efficiency,
hard to reconcile with a standardized cabling architecture.

TIA-942
Structured cabling is, by it’s philosophy, universal and
that means it makes compromises in efficiency to allow more
application flexibility. Data centers are so focused on
efficiency that such an approach for cabling is often not
acceptable - see OCP or Open 19 above. There are also issues
with the points of view – continuing to think that UTP
copper cable is the primary cabling, including legacy
systems like T-1 (1.5Mb/s) in the access provider connection
options, and even looking to having several interconnects
for parallel MPO-connector optics where the networks require
such low loss budgets that multiple MPO connections will
cause cabling to exceed the allowable power budgets.
Data Center Cabling Designs
Modern data centers have adopted unique cabling
architectures that are appropriate for data center equipment
usage. We will look at the two most common designs,
“top-of-rack” and “end-of-row.”
Top Of Rack

You will often hear about “top of rack” designs. In this
design, the servers are in a rack with the switches that
serve them. This makes the connection between the two very
short so less expensive copper cables can be used within the
rack – either UTP or CX-4, as well as fiber. This actually
limits the copper to each rack as other connections are made
on fiber. If the rack connections are limited to 10G, this
will save money. And there are options for low power
10G for short links on copper (CX-4 and proprietary UPT
implementations) that save lots of power.
The downside of this design is there are usually more
switches to manage (i.e. keeping track of software
upgrades). But the upside it the ease in cabling
installation and management.
End of Row

What’s called “End-of-Row” design comes from the idea that a
rack of switches is on the end of a row serving the servers
in that row and connecting to other racks of switches in
other parts of the data center. The Server racks and switch
racks are connected by UTP for up to 10G or fiber for any
speed. The switch racks connect to Interconnection and SAN
switches generally over fiber optics.
End-of-Row racks of switches can be placed in the middle of
a row or even be used to connect several rows of servers,
depending on the density of equipment. Redundancy is often
included, even having two EoR racks serving the same
servers.
Racks will generally have patch panels that allow equipment
in the racks to connect over short patchcords to the large
bundles of cables between the racks. Care must be taken to
keep the patchcords of reasonable length otherwise the front
of the rack is likely to become an unmanageable mess.
Some designers seem to think that EoR is more efficient from
the switch standpoint (more port utilization) and easier to
manage. The downside is the architecture is less
flexibility, the need to manage large bundles of UTP cables,
more cabling infrastructure, and lack of upgrading
capability beyond 10G until (unless?) Cat 8 becomes real.
Making Connections
Data centers can have lots of connections. Sometimes
they
grow “organically” and the back side of the racks
begin to
look like this. Good luck troubleshooting this
system! This is one of the reasons that high fiber count cables are used
in data centers.

Data centers generally use Ethernet, although Fibre Channel
(yes, it’s spelled “fibre”) has been used for storage area
networks (SANs). However the trend is to now carry Fibre
Channel over Ethernet to simplify the overall data center
networks.
Lots of choices are available for data center media –
classic UTP cable, coax, multimode or singlemode fiber and
hybrid active optical cables (AOCs) that are fiber cables
with permanently attached transceivers.
Data Center Cabling Options
Media
|
1Gb/s
|
10Gb/s
|
40Gb/s
|
100Gb/s
|
UTP
|
Cat
5E
|
Cat
6A
|
Cat
8
|
NA
|
Coax
(short)
|
CX
|
CX-4,
SFP+
|
CR4
|
CR10,
CR4
|
MM
Fiber
|
OM2/3/4
|
OM3/4
|
OM3/4
Parallel, 8 fibers
WDM, 2 fibers, proposed
|
OM3/4
Parallel, 20 fibers or 8 fibers
OM5
CWDM, 2 fibers
|
SM
Fiber
|
OS1/2
|
OS1/2
|
OS1/2,
WDM
|
OS1/2,
WDM |
AOC
(short)
|
NA
|
SFP+
|
QSFP+/SFP+
|
CXP
|
Data centers are now using faster connections
at 200/400/800 gigabits/s and 1.6/3.2 terabits/second in the future. At
higher speed the fiber will be all singlemode.
Here is a quick summary of data center cabling options. Coax
and AOCs are used for short (!<5m) links, UTP can be used
to its usual 90+10m limit, MM fiber can work over a range of
450 down to 100m depending on the type of fiber chosen but
is very limited on power budget, meaning the cable plant
must be low loss. SM fiber is becoming standard because
it offers the usual fiber advantages – basically unlimited
bandwidth and distance.

Cat
6A UTP works with 10G Ethernet, Cat 5E with 1G Ethernet.
It’s relatively cheap but consumes `5x as much power as a
fiber link. It will also require much more space in the
cable trays or under the floor – probably too bulky for
under the floor often – and for Cat 6A at 10G you have to
worry about alien crosstalk from cable to cable.
One big disadvantage of the copper is the power
consumption of transceivers. Due to the digital processing
needed to make a copper solution work, a copper
transceiver may consume up to 5-6W of power – almost ten
times as much as a fiber transceiver that consumes only
0.5-1W.
A new UTP standard for Category 8 cabling for short
(<30m) links in data centers has been approved. Cat 8 is
only intended for short links and will consume lots of
power. Somebody will probably find a way to make UTP work at
100G too, but who knows how much power that will take.

This is a CX-4 cable for 10G which uses four small coax
cables. Good for short links - ~5m – connections on a rack
or rack to an adjoining rack. It requires a SFP module
interface.

Active optical cables use mm parallel optics with a
pluggable transceiver permanently attached to the cable.
They are also used for short links, The transceivers plug
into SFP receptacles.

Multimode fiber has become widely used for up to 10G. VCSEL
laser sources are cheap and multimode fiber easy to install.
But MM is running out of bandwidth at 10G so parallel optics
with separate 10G channels are used at 40G and 100G.
40G uses 4x10G channels and 100G uses 10x10G channels that
has a major impact on the fiber count needed to support
equipment. MM links at 10G are also power limited due to the
bandwidth penalty caused by the limited modal bandwidth of
the multimode fiber. MM links may only have ~<2dB loss
budgets meaning that the data center cable cannot have many
interconnections especially with the MPO multifiber array
connectors which are inherently higher loss than single
fiber ceramic-ferrule connectors like LCs and SCs. For
example, if one uses the TIA specification for connector
loss of <0.75dB/ connection (connector mated pair), one
could only have two connections in a cable plant link,
basically the two connections needed to go from the
permanently installed cable plant to the patchcords
connecting the equipment, e.g. no interconnections in the
installed cable plant.
A variation for MM fiber is short wavelength CWDM
using 4 VCSELs at wavelengths in the range of 850-950nm on
special fiber now designated OM5 or wideband MMF. This
promises to allow duplex links over MMF. The issues with
this method are availability
of components, particularly transceivers, cost
compared to SM fiber and of course the lifecycle cost when
it comes time to move up to 200G, 400G or more. See details
below.
Simplex or duplex MM like SM fiber uses LC
connectors
because they are used in the transceivers for their
smaller
size. Parallel optics and prefab cable assemblies
(more on
those later) use the MPO connector which has 12 or
24 fibers
per connector or 16/32 fibers per connector. The
limitation of parallel optics with MPO
connections includes the masses of fibers required
and the
fewer interconnects allowable because of the
typically
higher loss of the MPO connector. MPOs are also used
with singlemode fiber and even multicore fibers; a 24 fiber MPO with
4-core multicore fiber makes 96 connections, highly helpful when
connecting 1728, 3456 or 6912 fiber cables.

MPO connector - more
on MPO connectors and testing them
There are 40G and 100G solutions on multimode
fiber. 40G uses a 12 fiber MPO with 4 channels each at 10G
for transmit and receive on separate fibers, so there are 4
transmit and 4 receive fibers. Since the MPO connector has
12 fibers, the center 4 are unused.
100G uses 10 channels each at 10G for transmit and receive
on separate fibers on a 24 pin connector, so there are 10
transmit and 10 receive fibers. Since the MPO connector has
12 fibers in each row, the center 4 are unused.
There is a version
of 100G being developed that uses 4 X 25g channels which
will have shorter reach. This design should use a connection
scheme like 40G on a 12 fiber connector.
MM transceivers use inexpensive 850nm VCSELs so the
transceivers are cheaper than singlemode but the fiber optic
cable plant uses many multimode fibers so the cable plant is
more expensive.
Singlemode fiber has practically unlimited bandwidth and
distance capability when used in data centers. Unlike the
parallel 10G channels used with MM fiber, singlemode uses
wavelength division multiplexing – WDM – to transmit
multiple channels over one fiber at different wavelengths.
Thus 40G uses 4X10G wavelengths and 100G is achieved using
4x25G wavelengths. CWDM transceivers cost more than parallel
MM transceivers at the current time, but the cabling cost is
much lower and expected higher quantity usage will
drive costs down. Look what 100million users did for
the lasers and CWDM used in fiber to the home (FTTH.)
Both MM and SM fiber use LC connectors or MPO
connectors depending on the transceivers and racks used. SM designs
may incorporate LC-APC connectors to reduce
reflectance. MPO connectors also use an angled termination.
Moving Faster Data over
Cabling
Every data center begins with fiber optic
connections to the Internet, usually to several providers
for redundancy. Entrance facilities must be provided for
multiple cables connecting to the outside communications
networks. Incoming cables will terminate in racks with
connections to routers that in turn connect to the servers
hosted in the data center. These connections will carry vast
quantities of data over singlemode optical fibers at
10-100Gb/s.
Within the data center, the goal is to move data as fast as
possible with the lowest latency and that means using the
fastest possible data communications links. Gigabit Ethernet
is too slow. 10 gigabit Ethernet and Fibre Channel are
commonly used today. Fibre Channel is moving to 16 Gb/s and
Ethernet is headed for 40 Gb/s and 100 Gb/s. The big data
center users want 40/100 Gb/s as fast as possible and are
pushing network standards committees and manufacturers to
produce useable products as soon as possible.
At 10 Gb/s, standard data links use multimode or singlemode
fiber optics, coax cables or Category 6A unshielded twisted
pair links (see table above). Of the three, fiber is the
most reliable and has the lowest power consumption,
especially if the links are long, saving as much as 70% over
UTP copper links. Up to about 10 meters (33 feet)
10GBASE-CX4 on coax can be used on very short links
effectively. Cat 6A consumes lots of power to transmit 10
Gb/s on longer links and generates more heat. Many data
centers use coax for short links and fiber for longer links,
but Cat 6A continues to be developed for lower power and is
becoming more widely used.
The next step up from 10G is to 40G or 100G. Some users are
thinking about using the UTP Cat 8 cable in a rack as part
of a 40G upgrade.
Some big users are
skipping 40G and going right to 100G, generally on SM fiber.
The 40/100 Gb/s MM standards call for multiple 10 Gb/s
channels run over parallel multimode optical fiber cables,
the new MM fibe rWDM (see below) or WDM
on singlemode fiber. The MM links require 8 fibers for 40
Gb/s (two fibers transmitting in opposite directions for
each 10 Gb/s link) and 20 fibers for 100 Gb/s. These links
use the MTP multifiber connector in 12 and 24 fiber
configurations, the same connector used on prefab systems
today so there are some unused fibers. Singlemode generally
uses LC connectors. The largest users of data centers have
expressed a preference for WDM on SM fiber for reduced
cabling bulk and cost.
Here is
a table of the options for faster speeds. There is a lot of
activity to add new variations, e.g. 200G and 400G and up in
the standards committees, so keeping up with the latest
standards requires checking the appropriate standards
groups.
Port
|
Links
|
Fibers/Connectors |
Limitations
|
Issues
|
| 40Gb,
850nm multimode |
4
X 10Gb, parallel |
8
OM3/4, MTP/MPO |
100-125m
|
Manage
fibers in groups of 4
|
40Gb,
850nm MM, CWDM
|
4
X 10Gb,CWDM |
2
OM5 |
100-125m |
Limited
availability |
| 40
Gb, 1300 nm singlemode |
4
X 10Gb, CWDM |
2
OS1/OS2, SC or LC |
10,
40 km
|
Premises
singlemode
|
| 40
Gb, 1550 nm singlemode |
1
X 40Gb |
2
OS1/OS2, SC or LC |
2
km
|
Premises
singlemode |
| 100
Gb, 850nm multimode |
10
X 10Gb, or 4 X 25G parallel |
20
OM3/4, MTP/MPO |
100-125m |
Manage
fibers in groups of 10 or 12? |
100
Gb, 850nm, CWDM
|
4
X 25G, CWDM |
2
OM5 |
100-125m |
Limited
availability |
| 100Gb.
1300 nm singlemode |
4
X 25Gb, CWDM |
2
OS1/OS2, SC or LC |
10,
40 km |
Premises
singlemode |
800G,
Intel SPT, 1300 nm multimode (more,
FOA NL 9/13)
|
32
X 25Gb/s
|
64
special MM fibers, custom 64 fiber expanded beam
connector - MXC
|
300
m
|
Proprietary
fiber and connector, 64 fiber cables, prefab only
|
Beyond 10G, the issue is cost as well as cabling bulk. MM
fiber generally uses parallel optics with 10G channels to
build higher speeds. Short wavelength WDM is still limited
in availability or support. The VCSEL sources used for MM
are cheaper but it requires many more fibers and that can
offset the higher cost of SM WDM transceivers. SM at 100G is
especially advanced, using 4x25G channels over each fiber,
making it much less complex in the cable plant.
Discussions with big data center owners and contractors
indicate a preference for going to SM. Transceivers are more
expensive but cabling is much cheaper and easier to install
and manage. SM also allows more flexibility in distance and
numbers of interconnections. MPO connectors used in parallel
optics have higher loss and the loss budgets are low, as low
as 2dB, limiting interconnections. And perhaps most
importantly, SM fiber allows for upgrades in equipment
speeds - into the terabits/second range - without replacing
cabling.
| Cabling |
40G
|
100G
|
MM
parallel
|
8
fibers
4 Tr - 4 Rcv
4 unused
|
20
fibers
10Tr - 10 Rcv
4 unused
or
8
fibers
4 Tr - 4 Rcv
4 unused |
MM
WDM (OM5)
SM WDM
|
2
fibers
|
2
fibers
|

Multimode
parallel optics uses lots of fibers in MPO array connectors.
The 12 fiber MTP connector used on MM 40 and 100 Gb/s links
and many prefab cable systems. 40G (4 x 10G) uses 4 fibers
at 10Gb/s in each direction (top connector.) 100G
(10 x 10G) uses either 10 fibers
at 10Gb/s in each direction (bottom connector.) or for
100G
(4 x 25G) 4 fibers
at 25Gb/s in each direction (top connector.)
Compare a 100G switch with 20 ports. Using MM fiber on a
10X10G link, you will have 20 MPO 24 fiber connectors and
480 fibers serving a single switch. *Think how many fibers
you need for a rack! And about 15% of those fibers are
wasted because the MPO connector has unused fibers, unless
the connectors are only loaded for 8 or 10 fibers or you
use one of the complicated MPO splitting schemes
with modules that do the arranging of fibers..
At 40G (4 X10G) or 100G (4 X 25G), you lose 1/3 of all the
fibers, but the 20 port switch needs only 240 fibers, half
as many.
With SM, each switch needs 40 fibers and 20 duplex LC
connectors.
SM has advantages on installation time, cabling cost,
testing time and cost, probably enough to balance out the
higher cost of transceivers – and then think about the
ease of upgrades.
Even inside the servers, increasing speed and
reducing power has led to the development of optical fiber
interconnects. Intel is actively developing board level
interconnects for their products, touting all the usual
benefits of fiber.
Proposed Options - MM Fiber
WDM
Some new ideas are making MM fiber a possibility for up to
400G, or at least 100G on only two fibers. The idea
developed by Cisco and Finisar is to use short wavelength
WDM – wavelength division multiplexing – with VCSELs on an
upgraded OM4 fiber, now standardized as OM5. The wavelengths
uses are in the 840-940nm range with 30nm spacing. The fiber
needs to be modified to have modal dispersion increased at
longer wavelengths but benefits from the fact that the
chromatic dispersion is reduced at longer wavelengths.
Cisco is already using this technology and while it has been
standardized it is not widely available commercially.

This graphic courtesy Commscope, OFS and Finisar shows how
wide band MM fiber can be used for WDM up to 100G on 2
fibers and 400G on 8 fibers.
Switch manufacturers are also proposing new 25G and 50G
Ethernet options for server connections using MM fibers and
advanced high-speed 850nm VCSELs.
With the work done by OCP to get 100G
transceiver costs down almost 90% for data center
applications, the movement to singlemode in data centers
is nearing universal. 200/400/800G is commonplace and even 1.6 and 3.2T transceivers
are being tested already, showing the capability of
singlemode fiber.
Fiber Choices
After making the choice of MM or SM, there are other choices
to make, such as the fiber type.
With MM, do you use OM3 fiber or the higher bandwidth but
more costly OM4? Or maybe OM5 and hope that MM WDM products
will be developed? Do you choose a prefab or field
terminated installation. If field terminated, what kind of
connectors (MPOs are not a good choice for field
installation.) And if you have a choice, do you use regular
or bend-insensitive (BI) fibers? Considering how cramped
cables usually are in data centers, BI fiber is probably a
good choice. (But remember that mixing BI MM fiber and
regular MM fiber may incur excess losses when going from BI
to regular fiber and that reference test cables must be of
the same type fiber as the fibers being tested.)
Likewise, SM offers similar choices. OS1 fiber is standard
SM fiber cabled for premises use while OS2 is cabled for OSP
use and lower loss because of the cable design. Both are
“low water peak” fiber better for CWDM. And now that most SM fiber is bend-insensitive
(BI) fiber, they will perform better in cramped cable trays and
racks.
Specialty Fibers For Data Centers
Data centers have begun to use two specialty types of fibers, hollow core fibers (HCF) and multicore fibers (MCF).

Hollow core fibers are
used because the light travels about 50% faster because the light
travels in a gas instead of glass. HCF is being used to connect remote
data centers because the faster speed of light reduces data latency.
Multicore fiber is being used to increase the density of connections in
the data center cabling. A MCF with 4 cores quadruples the data
carrying capacity of a fiber and increases the cable and connection
density. Thus a 1728 fiber cable has 6912 data paths and a 24 fiber MPO
connector can make 96 fiber connections.
Cabling Design And
Installation
Many data centers will contain a mix of fiber, coax and UTP
cabling. The connections to the Internet coming in from the
outside world are going to be on singlemode fibers.
Multimode fiber, either OM3 or the new OM4 high bandwidth
fibers, are likely to be used for MM connections. Coax will
be used on very short connections or Cat 6A may be used for
short and medium length links. Another option for short
links is active optical cables. Much of the choice depends
on the data center design choices.
Whichever media is used for interconnects, one thing is
certain, there will be lots of cables! Cables from routers
to servers, servers to other servers or switches and
switches to storage devices. The volume of cables involved
and the number of routes they can follow make planning the
pathways and spaces carefully to prevent chaos in the data
center. Cables may be run overhead or under floors. All
cable trays must be properly sized for the expected cable
loads. Under floor trays are generally wire mesh types while
heavy-duty overhead racks are usually needed, especially
when expected to carry large quantities of heavy copper
cabling. Additional room should be provided for Cat 6A since
cables cannot be neatly bundled to save space, because that
may cause alien crosstalk between adjacent cables.

Prefab cable system with modular interface. More
on prefab cabling.
Because a Cat 6A or coax cable makes only one connection
link per cable, multi-fiber optical fiber cables are big
space savers. Prefabricated fiber optic cable systems using
multi-fiber MTP style connectors not only save space but
also installation time, since they just require installation
and plugging together, no termination or splicing required.
Fiber optic cables that are “armored” are sometimes used in
the under floor trays to prevent cable damage when more
cables are placed in the trays.

Armored indoor fiber optic cable
If one chooses to install cable and terminate onsite, the
installation is straightforward. Pull cables, set up a
termination station and go to work. One can use either
adhesive/polish or prepolished/splice connectors for single
fiber MM but singlemode is best installed by fusion splicing
on pigtails or using prepolished/splice connectors of the
type used often for fiber to the home. APC connectors for
singlemode connections might be a good idea as it reduces
reflectance and problems it can cause. MPO connectors are
generally supplied in prefab assemblies but can be
terminated by fusion-splicing pigtails onto cables.
Field termination in a data center can be a big project with
so many connections, so some users look to prefab
cable plants (preterminated cabling systems as some
manufacturers call them). The good news is they are quick to
install. Now for the bad news: The cable plant must be
carefully designed so it’s not too long (requiring excess
cable storage which may be hard to find in a crowded data
center, nor too short with obvious bad consequences. Prefab
cabling can be more costly than field termination. MPO
connectors have higher loss than LCs or SCs when some links
have very low loss budgets and can have higher reflectance
which can adversely affect data transmission. These
connectors are very sensitive to dirt and must be carefully
cleaned, even on the connectors with alignment pins. Special
microscopes are needed to inspect these connectors.
Whenever one is installing prefab or preterminated cables,
one must have protective covers over the connectors during
installation to prevent damage. Damaged cables will probably
be removed and replaced by a new cable which may take a few
weeks to get delivered.
If the system is prefab with LC modules as shown here,
testing is straightforward, but as you will see, parallel
optics with MPO connectors is more complicated to test.
Cable Testing
Cable testing is important for all cables. Cat 6A is highly
stressed at 10 Gb/s so all terminations must be carefully
made. Even fiber links, especially if they include multiple
connections, must be tested since link loss at 10 Gb/s and
above is quite small and intolerant of bad connections. MPO
parallel optics present a particular problem for testing as
there are few testers designed with MPO interfaces. MPO
connectors used in parallel optics and prefab cabling
systems and testing them. Various
methods of testing parallel optics are covered in the FOA
Guide section on testing.
Cable Documentation
Obviously cable plant documentation and labeling are
critically important. In a facility that may have thousands
of cables, it’s vitally important that each cable end and
each port be logically marked to allow moving, tracing,
testing and troubleshooting cables.
Powering And Cooling The Data Center
As noted above, data centers consume vast amounts of
power and require large uninterruptible power supplies for
reliability. All power requires conditioning for delicate
electronic modules. Many data centers run dual power systems
with dual power backup to ensure maximum reliability. This
means dual UPS setups, dual generators and dual power
distribution systems.

Battery backup and generator at a data center
Power cables are usually under the floor on separate aisles
from data cables.
The actual layout of power and data cables has to be
coordinated with the layout of equipment racks because
cooling of the equipment has become quite sophisticated.
Generally data centers are kept much cooler than regular
offices to ensure proper cooling for all the equipment.
Racks and electronics are designed for directional airflow
to keep hot air away from other electronics and feeding
cooling air to the racks. When you consider that the air
conditioning will use as much power as the servers, careful
design of air conditioning is very important. Cable racks
must not impede cooling airflow.
Because of the high power consumption, data centers have
become a major focus of research on how to reduce power.
Electronics manufacturers are developing lower power systems
and using lower power fiber optic data links. Even the
location of the data centers can affect the cost of power
and design of a data center. The owners of big data centers
like Google are well aware of the issues. In the Bay Area
near their headquarters, Google uses solar photovoltaic
systems to generate 30% of their power. Several major data
centers are located on the Columbia River so it can utilize
lower cost (and lower carbon) hydroelectric power.
Cooling is a big problem in data centers. A single rack can
use kW of power and most of it is converted to heat that
must be removed. It may take as much power for cooling a
data center as its equipment consumes. It's beyond the scope
of this page to cover cooling issues but there is plenty of
literature on the subject.
Security
Data centers are considered critical facilities and of
course involve massive investment. Owners invest millions in
preventing intrusion from the Internet from hackers and are
also concerned with physically securing the facility. A
typical data center will include state-of-the-art personnel
entry systems, intrusion alarms and numerous surveillance
cameras. This will often cover not only the actual building
but the area in which it is located. Some data center owners
even ban cell phones and WiFi from the facilities because of
worries about data interference.
Coordination is Key
While data centers tap all the resources of the user,
designer and the well-rounded contractor, it is important
that the contractor be involved with the customer from the
initial concept of the project. A successful data center
will involve coordination among the customer, vendors,
contractors and often even municipalities and utilities from
the beginning of the project. Each party should contribute
to the design to ensure that all issues like facility
design, communications, power and security are covered
properly.
Table
of Contents: The FOA Reference Guide To Fiber Optics
|